Outage planning results

Last updated: Tue, 19/10/2021 - 12:10
Your current search

Sites: all sites selected

Outages search found 3635 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
ISL 66BS CHANGE SI G 11/11/2021 - 17:30 11/11/2021 - 18:30 D PSO 1109873 Approved 07/05/2012 - 15:51
ARG KIK 1 SI G 15/11/2021 - 07:00 15/11/2021 - 07:30 D PSO 1110048 Approved 07/05/2012 - 15:51
ARG BLN 1 SI G 22/10/2021 - 18:00 22/10/2021 - 18:30 D PSO 1109485 Approved 07/05/2012 - 15:51
ARG KIK 1 SI G 19/11/2021 - 18:00 19/11/2021 - 18:30 D PSO 1110049 Approved 07/05/2012 - 15:51
ISL 220BS CHANGE SI G 10/11/2021 - 06:30 10/11/2021 - 07:30 D PSO 1109868 Approved 07/05/2012 - 15:51
PEN C 13 NNI G 01/11/2021 - 15:00 01/11/2021 - 18:00 D PSO 1109995 Approved 07/05/2012 - 15:50
HTI TMU 1 NNI G 29/10/2021 - 19:00 29/10/2021 - 19:30 D PSO 1109715 Cancelled 29/05/2015 - 10:44
PEN C 12 NNI G 01/11/2021 - 12:00 01/11/2021 - 15:00 D PSO 1109994 Approved 07/05/2012 - 15:50
PEN C 11 NNI G 01/11/2021 - 10:00 01/11/2021 - 12:00 D PSO 1109993 Approved 07/05/2012 - 15:50
OTA 220BS CHANGE NNI G 01/11/2021 - 18:00 01/11/2021 - 18:30 D PSO 1109853 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 01/11/2021 - 06:30 01/11/2021 - 07:00 D PSO 1109852 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 05/11/2021 - 18:00 05/11/2021 - 18:30 D PSO 1109847 Approved 07/05/2012 - 15:49
ALB C 2 NNI G 01/11/2021 - 08:30 01/11/2021 - 12:30 D PSO 1109840 Approved 07/05/2012 - 15:50
OTA 220BS CHANGE NNI G 28/10/2021 - 06:30 28/10/2021 - 07:00 D PSO 1109544 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 28/10/2021 - 18:00 28/10/2021 - 18:30 D PSO 1109545 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 27/10/2021 - 18:00 27/10/2021 - 18:30 D PSO 1109543 Approved 07/05/2012 - 15:49
WKM 220BS CHANGE NNI G 20/10/2021 - 06:30 20/10/2021 - 07:00 D PSO 1109497 Approved 07/05/2012 - 15:49
HTI DIS 54 NNI G 29/10/2021 - 05:30 29/10/2021 - 06:00 D PSO 1109713 Cancelled 29/06/2018 - 14:00
OTA 220BS CHANGE NNI G 27/10/2021 - 06:30 27/10/2021 - 07:00 D PSO 1109542 Approved 07/05/2012 - 15:49
OTA 220BS CHANGE NNI G 04/11/2021 - 06:30 04/11/2021 - 07:00 D PSO 1109844 Approved 07/05/2012 - 15:49
WKM 220BS CHANGE NNI G 28/10/2021 - 17:30 28/10/2021 - 18:00 D PSO 1109501 Approved 07/05/2012 - 15:49
HTI DIS 54 NNI G 29/10/2021 - 19:00 29/10/2021 - 19:30 D PSO 1109716 Cancelled 29/06/2018 - 14:00
WKM 220BS CHANGE NNI G 27/10/2021 - 06:30 27/10/2021 - 07:00 D PSO 1109472 Approved 07/05/2012 - 15:49
WKM 220BS CHANGE NNI G 27/10/2021 - 17:30 27/10/2021 - 18:00 D PSO 1109473 Approved 07/05/2012 - 15:49
HTI 97 87 VT57 NNI G 29/10/2021 - 19:00 29/10/2021 - 19:30 D PSO 1109714 Cancelled 29/06/2018 - 13:40
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.