Outage planning results

Last updated: Wed, 29/06/2022 - 13:10
Your current search

Sites: all sites selected

Outages search found 3475 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BPE TNG 1 SNI G 21/11/2022 - 07:30 22/11/2022 - 18:30 D RS 1112449 Approved 07/05/2012 - 15:52
BPE TNG 1 SNI G 14/11/2022 - 07:30 15/11/2022 - 18:30 D RS 1112378 Approved 07/05/2012 - 15:52
BPE TWC LTN 1 SNI G 13/12/2022 - 07:30 13/12/2022 - 18:30 D RS 1112381 Approved 07/05/2012 - 15:53
BPE TWC LTN 1 SNI G 13/03/2023 - 07:30 17/03/2023 - 18:30 C RS 1112384 Approved 07/05/2012 - 15:53
BPE TWC LTN 1 SNI G 15/12/2022 - 07:30 15/12/2022 - 18:30 D RS 1112382 Approved 07/05/2012 - 15:53
BPE WDV 1 SNI G 01/05/2023 - 08:00 05/05/2023 - 18:30 D RS 1112388 Approved 07/05/2012 - 15:52
BPE WDV 1 SNI G 24/11/2022 - 07:30 24/11/2022 - 18:30 D RS 1112386 Approved 07/05/2012 - 15:52
BPE WDV 1 SNI G 22/11/2022 - 07:30 22/11/2022 - 18:30 D RS 1112385 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 08/05/2023 - 08:00 12/05/2023 - 18:30 D RS 1112393 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 18/10/2022 - 07:30 18/10/2022 - 18:30 D RS 1112391 Approved 07/05/2012 - 15:52
BPE WDV 2 SNI G 23/11/2022 - 07:30 23/11/2022 - 18:30 D RS 1112392 Approved 07/05/2012 - 15:52
BPT CB 142 SI G 20/01/2023 - 08:00 20/01/2023 - 17:30 D RS 1113779 Approved 07/05/2012 - 15:52
BRB CB 138 NNI G 27/02/2023 - 07:00 28/02/2023 - 18:00 C RS 1113327 Approved 07/05/2012 - 15:49
BRB CB 148 NNI G 01/03/2023 - 07:00 02/03/2023 - 18:00 C RS 1113340 Approved 07/05/2012 - 15:49
BRB CB 158 NNI G 06/03/2023 - 07:00 07/03/2023 - 18:00 C RS 1113341 Approved 07/05/2012 - 15:49
BRB CB 168 NNI G 08/03/2023 - 07:00 09/03/2023 - 18:00 C RS 1113356 Approved 07/05/2012 - 15:49
BRB HPI 1 NNI G 10/04/2023 - 07:30 14/04/2023 - 18:30 C RS 1113433 Approved 07/05/2012 - 15:50
BRB HPI 1 NNI G 11/08/2022 - 07:00 11/08/2022 - 18:00 D RS 1112981 Cancelled 07/05/2012 - 15:50
BRB HPI 1 NNI G 28/11/2022 - 07:30 03/12/2022 - 18:30 C RS 1103183 Approved 07/05/2012 - 15:50
BRB HPI 1 NNI G 07/11/2022 - 07:30 12/11/2022 - 18:30 C RS 1103180 Approved 07/05/2012 - 15:50
BRB HPI 1 NNI G 26/07/2022 - 07:30 28/07/2022 - 18:30 C RS 1115928 Approved 07/05/2012 - 15:50
BRB MDN 1 NNI G 06/03/2023 - 07:00 08/03/2023 - 18:00 C RS 1113346 Approved 07/05/2012 - 15:49
BRB RTU 1 NNI G 19/07/2022 - 09:00 19/07/2022 - 16:00 D SCA 1116048 Approved 07/05/2012 - 15:49
BRB T2 NNI G 22/05/2023 - 07:00 26/05/2023 - 18:00 C RS 1113499 Approved 07/05/2012 - 15:49
BRB T3 NNI G 29/05/2023 - 07:00 02/06/2023 - 18:00 D RS 1113505 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.