Outage planning results

Last updated: Sun, 29/05/2022 - 14:10
Your current search

Sites: all sites selected

Outages search found 3440 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TKR FDR 2142 SNI L 07/06/2022 - 07:30 10/06/2022 - 17:30 C RS 1116455 Approved 26/05/2015 - 13:39
GFD LST 5 SNI L 07/06/2022 - 07:30 10/06/2022 - 17:00 C RS 1095076 Approved 07/05/2012 - 15:52
KWA CB 8 SNI G 09/06/2022 - 07:00 10/06/2022 - 17:00 C RS 1110450 Approved 07/05/2012 - 15:53
KWA T2 SNI G 09/06/2022 - 07:00 10/06/2022 - 17:00 C RS 1110449 Approved 07/05/2012 - 15:52
GFD HAY 2 SNI G 07/06/2022 - 07:30 10/06/2022 - 17:00 C RS 1104096 Approved 07/05/2012 - 15:52
KWA WIL 1 SNI G 09/06/2022 - 07:00 10/06/2022 - 17:00 C RS 1110451 Approved 07/05/2012 - 15:52
GFD T5 SNI G 07/06/2022 - 07:30 10/06/2022 - 17:00 C RS 1095070 Approved 07/05/2012 - 15:52
RDF WTU GXP TIE SNI G 10/06/2022 - 12:00 10/06/2022 - 16:30 D OTH 1116746 Approved 01/11/2013 - 08:32
BPE RTU 1 SNI G 10/06/2022 - 07:30 10/06/2022 - 16:00 D RS 1116888 Approved 07/05/2012 - 15:52
BRB T2 NNI G 10/06/2022 - 08:30 10/06/2022 - 15:00 D RS 1117033 Approved 07/05/2012 - 15:49
ROS FDR 2352 NNI L 30/05/2022 - 07:00 10/06/2022 - 15:00 C RS 1116165 Approved 23/03/2018 - 10:01
KMO TRK 2 PROT2 NNI G 10/06/2022 - 12:00 10/06/2022 - 15:00 D RS 1115004 Cancelled 07/05/2012 - 15:50
HEN MPE 2 PROT2 NNI G 10/06/2022 - 11:30 10/06/2022 - 13:30 D RS 1115040 Approved 17/12/2015 - 08:35
MPE FDR 232 NNI L 08/06/2022 - 09:00 10/06/2022 - 13:00 C RS 1116189 Approved 01/04/2015 - 13:13
KMO TRK 1 PROT2 NNI G 10/06/2022 - 08:00 10/06/2022 - 11:00 D RS 1115003 Cancelled 07/05/2012 - 15:50
HEN MPE 1 PROT2 NNI G 10/06/2022 - 08:30 10/06/2022 - 10:30 D RS 1115039 Approved 17/12/2015 - 08:34
HWB FDR 2422 SI L 07/06/2022 - 07:00 09/06/2022 - 19:00 C RS 1116507 Approved 01/05/2018 - 10:34
BLN FDR 2042 SI L 07/06/2022 - 07:30 09/06/2022 - 18:30 C RS 1101432 Cancelled 07/05/2012 - 15:51
KMO TMI 1 NNI G 07/06/2022 - 07:30 09/06/2022 - 18:30 C OPE 1115688 Approved 07/05/2012 - 15:50
KMO TRK 2 NNI G 07/06/2022 - 07:30 09/06/2022 - 18:30 C RS 1111047 Approved 07/05/2012 - 15:50
MNG ROS 1 NNI G 08/06/2022 - 07:00 09/06/2022 - 18:30 C OPE 1117031 Approved 07/05/2012 - 15:49
DOB T12 SI G 08/06/2022 - 07:30 09/06/2022 - 18:30 C RS 1115066 Approved 07/05/2012 - 15:52
TRK RTU 1 NNI G 07/06/2022 - 07:30 09/06/2022 - 18:30 D RS 1111048 Approved 07/05/2012 - 15:49
MNG ROS 2 NNI G 07/06/2022 - 07:30 09/06/2022 - 18:30 C RS 1101431 Approved 07/05/2012 - 15:49
ATU DOB 1 SI G 08/06/2022 - 07:30 09/06/2022 - 18:30 C RS 1115067 Approved 20/08/2018 - 12:36
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.