Outage planning results

Last updated: Mon, 16/05/2022 - 19:40
Your current search

Sites: all sites selected

Outages search found 3571 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
AVI 220CBF SI G 20/06/2022 - 07:30 23/06/2022 - 18:30 D RS 1101991 Approved 07/05/2012 - 15:51
BDE T2 SI G 05/06/2023 - 07:30 11/06/2023 - 17:30 D RS 1113970 Approved 07/05/2012 - 15:51
BDE 11BS A SI L 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113945 Approved 07/05/2012 - 15:51
BDE 11BS B SI L 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113963 Approved 07/05/2012 - 15:51
BDE CB 38 SI L 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113948 Approved 07/05/2012 - 15:51
BDE CB 38 SI L 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113966 Approved 07/05/2012 - 15:51
BDE C 1 SI G 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113946 Approved 07/05/2012 - 15:51
BDE C 2 SI G 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113947 Approved 07/05/2012 - 15:51
BDE 110BZ SI G 08/12/2022 - 07:30 08/12/2022 - 11:00 D RS 1113742 Approved 07/05/2012 - 15:51
BDE 11BZ SI L 06/12/2022 - 07:30 07/12/2022 - 17:30 D RS 1113740 Approved 07/05/2012 - 15:51
BDE 11BZ SI L 23/05/2022 - 08:00 26/05/2022 - 16:00 D RS 1104414 Approved 07/05/2012 - 15:51
BDE 11BZ SI L 16/05/2022 - 08:00 20/05/2022 - 16:00 D RS 1104427 Released 07/05/2012 - 15:51
BDE C 4 SI G 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113964 Approved 07/05/2012 - 15:51
BDE C 5 SI G 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113965 Approved 07/05/2012 - 15:51
BDE FDR 14 SI L 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113949 Approved 07/05/2012 - 15:51
BDE FDR 15 SI L 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113950 Approved 07/05/2012 - 15:51
BDE FDR 16 SI L 22/05/2023 - 07:30 22/05/2023 - 17:30 D RS 1113951 Approved 07/05/2012 - 15:51
BDE FDR 23 SI L 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113967 Approved 07/05/2012 - 15:51
BDE FDR 25 SI L 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113969 Approved 07/05/2012 - 15:51
BDE FDR 24 SI L 05/06/2023 - 07:30 05/06/2023 - 17:30 D RS 1113968 Approved 07/05/2012 - 15:51
ISL SVC 3 HVDC G 31/10/2022 - 08:00 04/11/2022 - 17:30 D RS 1113670 Approved 07/05/2012 - 15:51
GYM C1C2C3 SI G 01/07/2022 - 07:00 01/07/2022 - 18:30 D RS 1100179 Cancelled 07/05/2012 - 15:51
GYM C1C2C3 SI G 17/08/2022 - 08:30 17/08/2022 - 10:30 D PSO 1115729 Approved 07/05/2012 - 15:51
TWZ CB 2462 SI G 30/05/2022 - 07:00 30/05/2022 - 18:30 D RS 1104193 Approved 07/05/2012 - 15:51
OHB 1007 1107 SI G 10/01/2023 - 07:30 10/01/2023 - 17:30 D RS 1113757 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.