Outage planning results

Last updated: Sun, 29/05/2022 - 14:10
Your current search

Sites: all sites selected

Outages search found 3440 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HAM T8 NNI G 27/06/2022 - 07:00 08/07/2022 - 17:00 C RS 1116601 Approved 07/05/2012 - 15:49
TMN T5 SNI G 25/07/2022 - 07:00 09/08/2022 - 17:00 C RS 1116602 Approved 07/05/2012 - 15:52
TMN T8 SNI G 25/07/2022 - 07:00 09/08/2022 - 17:00 C RS 1116603 Approved 07/05/2012 - 15:52
HAM T7 NNI G 15/07/2022 - 07:00 29/07/2022 - 17:00 C RS 1116604 Approved 07/05/2012 - 15:49
HAM T8 NNI G 15/07/2022 - 07:00 29/07/2022 - 17:00 C RS 1116606 Approved 07/05/2012 - 15:49
HOR FDR 52 SI L 25/07/2022 - 07:30 25/07/2022 - 17:30 D RS 1116612 Approved 07/05/2012 - 15:51
HOR FDR 152 SI L 15/08/2022 - 07:30 15/08/2022 - 17:30 D RS 1116614 Approved 07/05/2012 - 15:52
PEN T10 NNI G 12/07/2022 - 07:00 12/07/2022 - 15:30 D OPE 1116615 Approved 07/05/2012 - 15:49
PEN CB 8612 NNI G 12/07/2022 - 07:00 12/07/2022 - 15:30 D OPE 1116616 Approved 17/03/2014 - 11:42
TWI CB 428 SI G 09/08/2022 - 07:30 09/08/2022 - 17:30 D RS 1116619 Approved 07/05/2012 - 15:51
TWI CB 468 SI G 09/08/2022 - 07:30 09/08/2022 - 17:30 D RS 1116620 Approved 07/05/2012 - 15:51
TWI CB 468 SI G 10/08/2022 - 07:30 10/08/2022 - 17:30 D RS 1116623 Approved 07/05/2012 - 15:51
TWI CB 478 SI G 10/08/2022 - 07:30 10/08/2022 - 17:30 D RS 1116624 Approved 07/05/2012 - 15:51
ROT DIS 367 NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D CLO 1116627 Approved 16/04/2015 - 09:43
ROT DIS 357 NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D CLO 1116628 Approved 16/04/2015 - 09:42
COL OTI 2 SI G 02/06/2022 - 06:30 03/06/2022 - 17:30 C RS 1116638 Approved 07/05/2012 - 15:51
MPE CB 252 NNI G 26/07/2022 - 07:30 28/07/2022 - 18:30 C OPE 1116642 Approved 07/05/2012 - 15:50
MPE CB 292 NNI G 26/07/2022 - 07:30 28/07/2022 - 18:30 C OPE 1116643 Approved 07/05/2012 - 15:50
BPE MHO 2 SNI G 01/06/2022 - 07:00 01/06/2022 - 19:00 D RS 1116666 Approved 07/05/2012 - 15:52
MHO T4 SNI G 01/06/2022 - 07:00 01/06/2022 - 19:00 D RS 1116667 Approved 07/05/2012 - 15:52
CBG T3 NNI G 05/09/2022 - 07:30 07/09/2022 - 17:30 C RS 1116668 Approved 07/05/2012 - 15:49
CBG T4 NNI G 12/09/2022 - 07:30 14/09/2022 - 17:30 C RS 1116669 Approved 07/05/2012 - 15:49
BLN RTU 1 SI G 01/08/2022 - 07:30 05/08/2022 - 18:30 D RS 1116674 Approved 07/05/2012 - 15:51
BLN RTU 2 SI G 01/08/2022 - 07:30 05/08/2022 - 18:30 D RS 1116675 Approved 07/05/2012 - 15:51
RDF 220BS CHANGE SNI G 08/08/2022 - 15:00 08/08/2022 - 15:30 D PSO 1116676 Approved 07/05/2012 - 15:53
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.