Outage planning results

Last updated: Wed, 29/06/2022 - 13:10
Your current search

Sites: all sites selected

Outages search found 3475 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
GLN T5 NNI G 07/09/2022 - 07:00 07/09/2022 - 18:00 D RS 1113021 Approved 07/05/2012 - 15:49
TMU FDR 22 NNI L 05/09/2022 - 07:00 09/09/2022 - 16:00 C RS 1114739 Approved 07/05/2012 - 15:49
TMU FDR 23 NNI L 14/03/2022 - 07:00 29/08/2022 - 16:00 C RS 1114740 Released 07/05/2012 - 15:49
GLN T6 NNI G 09/09/2022 - 07:00 09/09/2022 - 18:00 D RS 1113030 Approved 07/05/2012 - 15:49
HAM KPO 1 NNI G 19/11/2022 - 07:30 20/11/2022 - 18:30 C RS 1113136 Approved 07/05/2012 - 15:49
ROT TRK 1 NNI G 11/07/2022 - 07:30 13/07/2022 - 18:30 C RS 1111013 Approved 07/05/2012 - 15:49
ROT TRK 1 NNI G 13/02/2023 - 07:30 14/02/2023 - 18:30 C RS 1113310 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D RS 1116565 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 17/04/2023 - 08:00 19/04/2023 - 18:30 C RS 1113447 Approved 07/05/2012 - 15:49
ROT TRK 2 NNI G 24/04/2023 - 07:30 26/04/2023 - 18:30 C RS 1113467 Approved 07/05/2012 - 15:49
ROT WHE 1 NNI G 17/04/2023 - 08:00 19/04/2023 - 18:30 C RS 1113448 Approved 07/05/2012 - 15:49
TAK T5 NNI G 13/07/2022 - 07:30 13/07/2022 - 18:30 D RS 1112936 Approved 07/05/2012 - 15:49
TAK T5 NNI G 13/02/2023 - 07:30 18/02/2023 - 18:30 C RS 1103217 Approved 07/05/2012 - 15:49
TAK T5 NNI G 21/11/2022 - 07:30 26/11/2022 - 18:30 C RS 1103215 Approved 07/05/2012 - 15:49
TAK T8 NNI G 14/11/2022 - 07:30 18/11/2022 - 18:30 C RS 1113126 Approved 07/05/2012 - 15:49
TAK T8 NNI G 02/11/2022 - 08:00 02/11/2022 - 16:00 D RS 1097042 Approved 07/05/2012 - 15:49
TAK T8 NNI G 28/11/2022 - 07:30 03/12/2022 - 18:30 C RS 1103503 Approved 07/05/2012 - 15:49
TAK T8 NNI G 14/07/2022 - 07:30 14/07/2022 - 18:30 D RS 1112939 Approved 07/05/2012 - 15:49
TAK T8 NNI G 01/08/2022 - 07:30 11/08/2022 - 18:00 C RS 1111020 Approved 07/05/2012 - 15:49
TAK T8 NNI G 17/04/2023 - 07:30 21/04/2023 - 18:30 D RS 1113444 Approved 07/05/2012 - 15:49
TAK T8 NNI G 27/02/2023 - 07:30 04/03/2023 - 18:30 C RS 1103505 Approved 07/05/2012 - 15:49
TGA T1 NNI G 06/03/2023 - 07:30 07/03/2023 - 18:30 C RS 1113349 Approved 07/05/2012 - 15:49
TGA T1 NNI G 10/04/2023 - 07:30 12/04/2023 - 18:30 C RS 1113432 Approved 07/05/2012 - 15:49
GLN T5 NNI G 07/12/2022 - 07:00 07/12/2022 - 18:00 D RS 1113186 Approved 07/05/2012 - 15:49
ROT T3 NNI G 17/04/2023 - 08:00 19/04/2023 - 18:30 C RS 1113450 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.