Outage planning results

Last updated: Wed, 18/05/2022 - 17:55
Your current search

Sites: all sites selected

Outages search found 3601 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
TNG 220BS B SNI G 23/05/2022 - 07:30 23/05/2022 - 17:30 D RS 1101392 Approved 07/05/2012 - 15:52
TNG 220BS B SNI G 15/11/2022 - 07:30 15/11/2022 - 18:30 D RS 1112456 Approved 07/05/2012 - 15:52
TNG 220BS B SNI G 10/11/2022 - 07:30 10/11/2022 - 18:30 D RS 1112448 Approved 07/05/2012 - 15:52
TNG 220BS B SNI G 03/11/2022 - 07:30 03/11/2022 - 18:30 D RS 1112416 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 16/11/2022 - 07:30 16/11/2022 - 18:30 D RS 1112457 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 21/11/2022 - 07:30 21/11/2022 - 18:30 D RS 1112471 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 14/11/2022 - 07:30 14/11/2022 - 18:30 D RS 1112453 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 24/05/2022 - 07:30 24/05/2022 - 17:30 D RS 1101389 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 26/05/2022 - 07:30 26/05/2022 - 17:00 D RS 1115569 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 31/10/2022 - 07:30 31/10/2022 - 18:30 D RS 1112403 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 09/11/2022 - 07:30 09/11/2022 - 18:30 D RS 1112442 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 02/11/2022 - 07:30 02/11/2022 - 18:30 D RS 1112413 Approved 07/05/2012 - 15:52
TNG 220BS A SNI G 07/11/2022 - 07:30 07/11/2022 - 18:30 D RS 1112433 Approved 07/05/2012 - 15:52
TMU T2 NNI G 27/02/2023 - 07:30 08/03/2023 - 18:30 C RS 1100580 Approved 07/05/2012 - 15:49
TMU T2 NNI G 19/09/2022 - 07:00 23/09/2022 - 16:00 C RS 1115482 Approved 07/05/2012 - 15:49
TMU T2 NNI G 30/01/2023 - 07:00 01/02/2023 - 18:00 C RS 1113266 Approved 07/05/2012 - 15:49
TMU T1 NNI G 05/09/2022 - 07:00 09/09/2022 - 16:00 C RS 1115491 Approved 07/05/2012 - 15:49
TMU T1 NNI G 13/02/2023 - 07:30 22/02/2023 - 18:30 C RS 1100494 Approved 07/05/2012 - 15:49
TMU RTU 1 NNI G 07/09/2022 - 08:00 07/09/2022 - 14:00 D RS 1116337 Approved 07/05/2012 - 15:49
TMU RTU 1 NNI G 29/06/2022 - 08:00 29/06/2022 - 14:00 D RS 1111502 Approved 07/05/2012 - 15:49
TMU RTU 1 NNI G 28/09/2022 - 08:00 28/09/2022 - 14:00 D RS 1111490 Approved 07/05/2012 - 15:49
TMU RTU 1 NNI G 21/09/2022 - 08:00 21/09/2022 - 14:00 D RS 1116338 Approved 07/05/2012 - 15:49
TMU FDR 29 NNI L 16/05/2022 - 07:00 23/05/2022 - 16:00 C RS 1114746 Cancelled 07/05/2012 - 15:49
TMU FDR 29 NNI L 21/03/2022 - 07:00 23/09/2022 - 16:00 C RS 1111462 Released 07/05/2012 - 15:49
TMU FDR 28 NNI L 09/05/2022 - 07:00 23/05/2022 - 16:00 C RS 1114986 Cancelled 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.