Outage planning results

Last updated: Wed, 29/06/2022 - 13:10
Your current search

Sites: all sites selected

Outages search found 3475 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
PEN T23 NNI G 19/01/2023 - 07:00 20/01/2023 - 18:00 C RS 1113234 Approved 07/05/2012 - 15:49
CYD CB 488 SI G 11/07/2022 - 07:30 15/07/2022 - 18:30 C RS 1106499 Approved 07/05/2012 - 15:51
CYD CB 498 SI G 18/07/2022 - 07:30 22/07/2022 - 18:30 C RS 1106504 Approved 07/05/2012 - 15:51
CYD CB 508 SI G 09/08/2022 - 07:30 10/08/2022 - 18:30 C RS 1106520 Approved 07/05/2012 - 15:51
CYD CB 508 SI G 25/07/2022 - 07:30 29/07/2022 - 18:30 C RS 1106510 Approved 07/05/2012 - 15:51
CYD CML TWZ 1 SI G 25/12/2022 - 07:30 28/12/2022 - 18:30 C RS 1106574 Cancelled 07/05/2012 - 15:51
PEN T10 NNI G 28/11/2022 - 07:30 30/11/2022 - 18:29 C RS 1114260 Approved 07/05/2012 - 15:49
CYD CML TWZ 2 SI G 25/10/2022 - 07:30 31/10/2022 - 17:00 C RS 1113659 Approved 07/05/2012 - 15:51
CYD CML TWZ 2 SI G 27/09/2022 - 07:30 30/09/2022 - 18:30 C RS 1106553 Cancelled 07/05/2012 - 15:51
CYD ROX 1 SI G 30/08/2022 - 07:30 02/09/2022 - 18:30 C RS 1106541 Approved 07/05/2012 - 15:51
HEN HEP 4 NNI G 14/12/2022 - 07:30 16/12/2022 - 18:30 C RS 1113202 Approved 07/05/2012 - 15:49
OTA C 29 NNI G 13/07/2022 - 07:30 13/07/2022 - 18:30 C RS 1115369 Approved 07/05/2012 - 15:49
PEN T10 NNI G 30/11/2022 - 18:30 02/12/2022 - 18:30 C OPE 1116782 Approved 07/05/2012 - 15:49
WEL T2 NNI G 13/02/2023 - 07:00 17/02/2023 - 18:30 C RS 1102834 Approved 07/05/2012 - 15:49
PEN T10 NNI G 31/10/2022 - 07:30 04/11/2022 - 18:30 C OPE 1113104 Approved 07/05/2012 - 15:49
HAM KPO 1 NNI G 19/11/2022 - 07:30 20/11/2022 - 18:30 C RS 1113136 Approved 07/05/2012 - 15:49
PEN T10 NNI G 03/04/2023 - 07:30 08/04/2023 - 18:30 C OPE 1103195 Approved 07/05/2012 - 15:49
PEN FDR 1752 NNI L 19/01/2023 - 07:00 20/01/2023 - 18:00 C RS 1113232 Approved 07/05/2012 - 15:49
TMU 11BZ A1 NNI L 21/07/2022 - 08:00 22/07/2022 - 18:00 C RS 1117554 Approved 07/05/2012 - 15:49
PEN T10 NNI G 06/02/2023 - 07:00 07/02/2023 - 18:00 C OPE 1113280 Approved 07/05/2012 - 15:49
PEN T10 NNI G 08/05/2023 - 07:30 13/05/2023 - 18:30 C OPE 1103208 Approved 07/05/2012 - 15:49
TMU 11BZ A2 NNI L 21/07/2022 - 08:00 22/07/2022 - 18:00 C RS 1117555 Approved 07/05/2012 - 15:49
PEN T10 NNI G 01/05/2023 - 07:00 04/05/2023 - 18:00 C OPE 1113480 Approved 07/05/2012 - 15:49
DOB T2 SI G 05/12/2022 - 07:30 09/12/2022 - 16:30 C RS 1113734 Approved 07/05/2012 - 15:51
DOB T1 SI G 05/09/2022 - 08:00 09/09/2022 - 17:30 C RS 1113600 Approved 07/05/2012 - 15:51
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.