Outage planning results

Last updated: Mon, 04/07/2022 - 16:40
Your current search

Sites: all sites selected

Outages search found 3439 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
HEP FDR 2252 NNI L 12/03/2023 - 07:30 12/03/2023 - 18:30 D RS 1117429 Approved 17/11/2015 - 09:59
HEP FDR 2322 NNI L 02/04/2023 - 07:30 02/04/2023 - 18:30 D RS 1117439 Approved 17/11/2015 - 09:59
HEP FDR 2342 NNI L 02/04/2023 - 07:30 02/04/2023 - 18:30 D RS 1117440 Approved 17/11/2015 - 10:00
HEP CB 2158 NNI L 12/03/2023 - 07:30 12/03/2023 - 18:30 D RS 1117425 Approved 17/11/2015 - 10:01
HEP CB 2158 NNI L 19/02/2023 - 07:30 19/02/2023 - 18:30 D RS 1117392 Approved 17/11/2015 - 10:01
HEP CB 2278 NNI L 12/03/2023 - 07:30 12/03/2023 - 18:30 D RS 1117424 Approved 17/11/2015 - 10:01
HEP CB 2278 NNI L 02/04/2023 - 07:30 02/04/2023 - 18:30 D RS 1117438 Approved 17/11/2015 - 10:01
HEP 33BZ NNI L 06/03/2023 - 13:30 06/03/2023 - 18:30 D RS 1117419 Approved 17/11/2015 - 10:02
HEP 33BZ NNI L 18/02/2023 - 08:30 18/02/2023 - 18:30 D RS 1117389 Approved 17/11/2015 - 10:02
HEP 33BS K NNI L 19/02/2023 - 07:30 19/02/2023 - 18:30 D RS 1117391 Approved 17/11/2015 - 10:03
HEP 33BS L NNI L 12/03/2023 - 07:30 12/03/2023 - 18:30 D RS 1117423 Approved 17/11/2015 - 10:03
MPE FDR 232 NNI L 23/11/2022 - 07:30 23/11/2022 - 18:30 C RS 1113147 Cancelled 01/04/2015 - 13:13
MPE FDR 342 NNI L 24/11/2022 - 07:30 24/11/2022 - 18:30 D RS 1113167 Approved 01/04/2015 - 13:18
ROT DIS 357 NNI G 01/08/2022 - 07:30 01/08/2022 - 18:30 D CLO 1116628 Approved 16/04/2015 - 09:42
ROT DIS 357 NNI G 11/07/2022 - 07:30 13/07/2022 - 18:30 C CLO 1111040 Approved 16/04/2015 - 09:42
PEN RTU 2 NNI G 13/12/2022 - 08:00 15/12/2022 - 18:00 D RS 1117178 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 06/12/2022 - 08:00 08/12/2022 - 18:00 D RS 1117176 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 30/11/2022 - 08:00 01/12/2022 - 18:00 D RS 1117174 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 16/11/2022 - 08:00 16/11/2022 - 18:00 D RS 1117170 Approved 20/05/2013 - 15:20
PEN RTU 2 NNI G 09/11/2022 - 08:00 09/11/2022 - 18:00 D RS 1117168 Approved 20/05/2013 - 15:20
BOB 110BZ NNI G 12/09/2022 - 07:00 12/09/2022 - 18:00 D RS 1114453 Approved 13/11/2013 - 10:42
BOB 110BZ NNI G 11/10/2022 - 07:30 12/10/2022 - 18:00 D RS 1114503 Approved 13/11/2013 - 10:42
BOB 110BZ A NNI G 15/09/2022 - 07:30 15/09/2022 - 18:00 D RS 1111605 Cancelled 13/11/2013 - 10:43
PEN CB 8612 NNI G 04/07/2022 - 06:00 07/07/2022 - 18:00 D OPE 1117905 Released 17/03/2014 - 11:42
PEN CB 8612 NNI G 12/09/2022 - 07:30 23/09/2022 - 18:30 C OPE 1116360 Approved 17/03/2014 - 11:42
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.