Outage planning results

Last updated: Wed, 18/05/2022 - 21:40
Your current search

Sites: all sites selected

Outages search found 3588 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
BRK WGN GXP TIE 1 SNI G 25/05/2022 - 06:30 25/05/2022 - 19:00 D OTH 1116804 Approved 27/09/2021 - 11:56
BEN HAY 1 HVDC H 26/05/2022 - 07:30 26/05/2022 - 17:00 D RCB 1116659 Approved 07/05/2012 - 15:49
HTI CB 2188 NNI L 27/05/2022 - 07:30 27/05/2022 - 18:30 D RS 1115082 Cancelled 04/02/2020 - 15:28
GFD FDR 2252 SNI L 05/07/2022 - 08:00 05/07/2022 - 16:00 D RS 1116511 Approved 30/09/2021 - 14:56
MNI FDR 2722 SNI L 19/07/2022 - 07:30 19/07/2022 - 18:00 D RS 1101195 Cancelled 21/08/2019 - 09:50
HAY SC 1 HVDC H 04/07/2022 - 07:00 15/07/2022 - 18:00 D RS 1114018 Approved 07/05/2012 - 15:49
HTI FDR 2162 NNI L 25/05/2022 - 07:30 25/05/2022 - 18:30 D RS 1111691 Cancelled 04/02/2020 - 15:30
HAY SC 3 HVDC H 01/05/2023 - 07:00 05/05/2023 - 18:00 D RS 1114021 Approved 07/05/2012 - 15:49
LTN TUR AI PROT1 SNI G 24/05/2022 - 07:00 24/05/2022 - 17:00 D RS 1114049 Approved 08/12/2021 - 14:22
LTN TUR AI PROT2 SNI G 24/05/2022 - 07:00 24/05/2022 - 17:00 D RS 1114050 Approved 08/12/2021 - 14:25
TMU 11kV AFD B1 NNI L 13/06/2022 - 07:30 13/06/2022 - 17:00 D RS 1114909 Approved 03/03/2022 - 08:11
TMU 11kV AFD B2 NNI L 14/06/2022 - 07:30 14/06/2022 - 17:00 D RS 1114910 Approved 03/03/2022 - 08:12
WHU 33kV AFD BUS K NNI L 15/06/2022 - 07:30 15/06/2022 - 17:00 D RS 1114911 Approved 03/03/2022 - 08:17
WHU 33kV AFD BUS L NNI L 16/06/2022 - 07:30 16/06/2022 - 17:00 D RS 1114912 Approved 03/03/2022 - 08:19
WKO 33kV AFD BUS L NNI L 21/06/2022 - 07:30 21/06/2022 - 17:00 D RS 1114914 Approved 03/03/2022 - 08:21
WKO 33kV AFD BUS K NNI L 20/06/2022 - 07:30 20/06/2022 - 17:00 D RS 1114913 Approved 03/03/2022 - 08:21
HOB PEN 1 PROT2 NNI G 09/06/2022 - 12:30 09/06/2022 - 14:30 D RS 1115042 Approved 09/03/2022 - 13:02
HTI 33BZ K NNI L 27/05/2022 - 07:30 27/05/2022 - 18:30 D RS 1115089 Cancelled 11/03/2022 - 10:14
HTI 33BZ L NNI L 27/05/2022 - 07:30 27/05/2022 - 18:30 D RS 1115090 Cancelled 11/03/2022 - 10:20
CCT 327543 VOC CAL NNI G 22/05/2022 - 00:00 22/05/2022 - 06:00 D RS 1116595 Approved 17/03/2022 - 16:36
OTA T3 PROT2 NNI G 21/06/2022 - 10:00 21/06/2022 - 16:00 D RS 1115440 Approved 24/03/2022 - 08:41
OTA T4 PROT2 NNI G 22/06/2022 - 08:00 22/06/2022 - 12:00 D RS 1115442 Approved 24/03/2022 - 08:43
OTA T5 PROT2 NNI G 22/06/2022 - 13:00 22/06/2022 - 18:00 D RS 1115443 Approved 24/03/2022 - 09:48
PEN T10 PROT2 NNI G 24/06/2022 - 08:00 24/06/2022 - 12:00 D RS 1115446 Approved 24/03/2022 - 09:50
ARI KIN 1 NNI G 27/03/2023 - 07:00 27/03/2023 - 18:00 D RS 1113387 Approved 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.