Outage planning results

Last updated: Thu, 17/06/2021 - 16:40
Your current search

Sites: all sites selected

Outages search found 3544 results

Outage block ID Region Control Start End Type Nature Window ID Window status Lodged
MST FDR 2212 SNI L 16/07/2021 - 07:30 16/07/2021 - 18:30 D RS 1095834 Cancelled 07/05/2012 - 15:53
MST FDR 2222 SNI L 19/07/2021 - 07:30 19/07/2021 - 18:30 D RS 1095837 Cancelled 07/05/2012 - 15:53
MST FDR 2242 SNI L 20/07/2021 - 07:30 20/07/2021 - 18:30 D RS 1095838 Cancelled 07/05/2012 - 15:53
MST FDR 2252 SNI L 21/07/2021 - 07:30 21/07/2021 - 18:30 D RS 1095839 Cancelled 07/05/2012 - 15:53
OWH T1 NNI G 02/08/2021 - 07:30 06/08/2021 - 18:30 C RS 1095856 Approved 07/05/2012 - 15:49
OWH T2 NNI G 30/08/2021 - 07:30 03/09/2021 - 18:30 C RS 1095857 Approved 07/05/2012 - 15:49
KIK STC 2 HVDC G 06/09/2021 - 07:30 10/09/2021 - 18:30 C RS 1095992 Approved 07/05/2012 - 15:52
KIK STC 2A HVDC G 06/09/2021 - 07:30 10/09/2021 - 18:30 C RS 1095993 Approved 07/05/2012 - 15:52
KIK STC 2B HVDC G 06/09/2021 - 07:30 10/09/2021 - 18:30 C RS 1095994 Approved 07/05/2012 - 15:52
MHO T4 SNI G 21/06/2021 - 08:00 25/06/2021 - 17:00 D RS 1096030 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 21/06/2021 - 08:00 25/06/2021 - 17:00 D RS 1096031 Approved 07/05/2012 - 15:52
MHO T4 SNI G 12/07/2021 - 07:00 16/07/2021 - 17:00 C RS 1096032 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 12/07/2021 - 07:00 15/07/2021 - 17:00 C RS 1096033 Approved 07/05/2012 - 15:52
MHO FDR 2142 SNI L 26/07/2021 - 07:00 28/07/2021 - 17:00 C RS 1096034 Approved 31/01/2020 - 16:07
MHO T3 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096035 Approved 07/05/2012 - 15:52
BPE MHO 1 SNI G 02/08/2021 - 07:00 04/08/2021 - 17:00 C RS 1096036 Approved 07/05/2012 - 15:52
MHO T4 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096037 Approved 07/05/2012 - 15:52
BPE MHO 2 SNI G 09/08/2021 - 07:00 11/08/2021 - 17:00 C RS 1096038 Approved 07/05/2012 - 15:52
ALB 224 267 317 NNI G 13/09/2021 - 08:00 15/09/2021 - 18:00 C RS 1096165 Approved 07/05/2012 - 15:50
ALB CB 298 NNI G 13/09/2021 - 08:00 15/09/2021 - 18:00 C RS 1096166 Approved 07/05/2012 - 15:49
ALB C 1 NNI G 13/09/2021 - 08:00 15/09/2021 - 18:00 C RS 1096167 Cancelled 07/05/2012 - 15:49
ALB FDR 262 NNI L 13/09/2021 - 08:00 15/09/2021 - 18:00 C RS 1096168 Approved 07/05/2012 - 15:49
WKM RTU 1 NNI G 22/06/2021 - 07:30 22/06/2021 - 16:00 D RS 1096415 Approved 07/05/2012 - 15:49
NSY ROX 1 SI G 04/10/2021 - 07:30 25/11/2021 - 18:30 C RS 1096565 Approved 07/05/2012 - 15:51
CBG T3 NNI G 14/06/2021 - 07:30 18/06/2021 - 18:30 C RS 1096673 Released 07/05/2012 - 15:49
CSV

Disclaimer - Grid Outage Information

While Transpower makes reasonable efforts to ensure the accuracy of Outage and Plant Request Plans and other grid outage information posted on this website, Transpower does not give any warranty, guarantee or other assurance as to the content of this information, its accuracy, completeness, timeliness or fitness for any particular purpose. Outage and Plant Request Plans may change at any time due to Transpower or Customer requirements, and in particular the start and end times are a guide only and the times equipment is actually removed from, or returned to, service may vary within the planned period. To the full extent permissible at law Transpower disclaims all responsibility for any damage or loss (including without limitation, financial loss, damage to any equipment, loss of profits or other incidental or consequential losses) arising in contract, tort or otherwise from the use of any Outage or Plant Request Plans or other grid outage information appearing on this website, or from any action or decision taken as a result of using any such plan or information.

By downloading and using the Outage and Plant Request Plans and any other grid outage information you have agreed not to make any claims against Transpower for any loss or damage that may arise as a result of your reliance on such information.