TPM Development Project questions & answers

Subscribe for updates

Subscribe to this page to receive email notifications when this page has been updated.

Enter your email address to subscribe to this page.

We're here to answer your questions throughout the development of our TPM proposal. Feel free to send questions to tpm@transpower.co.nz or read our existing answers here.  

Questions and responses are listed by reverse chronology - the most recent questions and answers appear first. Where more than one question is asked in a single email, questions are numbered within each date entry.

17 November 2020 (Trustpower) - TPM Options consultation - download [ pdf 274.52 KB ].

29 October 2020 (Mercury) - First mover disadvantage consultation - download.

21 October 2020 (Refining NZ) - Connection Charges, focus area 7 - download.

23 September 2020 (Trustpower) - Forthcoming workshops on TPM congestion charge - download.

7 September 2020 (MEUG) - Breakdown of costs by individual GXP and GIP  - download.

7 September 2020 (MEUG) – Questions addressing the Connection Charges Consultation - download.

18 August 2020 (IEGA NZ) - Transitional peak charge in project timeline - download.

 

17 November 2020 (Trustpower) - TPM Options consultation

Question: To help with understanding how the new BBC and reallocator arrangements will work in practice, would it be possible for Transpower to provide a case study for a more complex transmission investment project?  

While a detailed case study could usefully be walked through during one of the scheduled drop in sessions, it would also be valuable to provide a written document containing the details to enable greater reflection and identification of any practical and/or philosophical issues that might emerge.

For example, it would be useful to apply the proposed new arrangements to an upcoming “deep” investment (i.e. HVDC capacity upgrade project etc) where the need for the investment is largely driven by forecasts of what is predicted to occur in the future. It would also be useful to consider how the methodology works on a retrospective basis for a deep investment.

We have made this suggestion previously in response to the case studies that Transpower provided as part of its submission to the Authority on the third TPM issues paper. Attached is the relevant expert report from Dave Smith on this matter in case this is of help (refer to section on GIT retrospective).  [This is included in the download above for this question.]


Answer: 

At this stage in the TPM development process we are not able to provide a case study, particularly for a deep/complex interconnection investment.  The current consultation is seeking views on options and concepts relevant to the key design decisions we need to make in order to develop case studies of the type you’re interested in. These design decisions will inform our preliminary proposal for the BBC component of the new TPM, which must be submitted to the EA for the Checkpoint 2 process. 

We are interested to hear the views of our stakeholders, which might include views about any practical difficulties of applying BBC options to different types of investment, including the ‘deep’ type your question relates to.

 

29 October (Mercury) – First Mover Disadvantage Consultation

Question: Could you clarify whether the word “not” is missing from this sentence? I assume that is the case but just wanted to make sure as it may change how we approach this issue/question.

 

 

 

 

 

 

 

[Page 9 of First Mover Disadvantage Consultation paper]

 

Answer: Thank you for your question. You are correct – the word “not” is missing from para 27. It should read “Our initial thinking is Nova’s suggestion should not be adopted because…”. We have updated the consultation document to rectify this.

 

21 October 2020 (Refining NZ) - Connection Charges Summary and response document, focus area 7

Question: 

I would like your clarification around the Transpower’s response on Area Focus 7:  Connection assets decommission costs.

I think the language use on the summary and response document on page 14 is confusing, as it states:

“Transpower response: We consider legitimate concerns have been raised about a “last man standing” problem and retrospective application of this proposal. Based on our consideration of submissions, our thinking is now that it would be better to continue to allocate connection asset decommissioning costs to all customers connected to the asset, regardless of the reason for decommissioning. This would mean that the cost recovery would default to the residual charge. We will make final decisions as part of the finalisation of our TPM proposal.”

Can you please clarify if Transpower is now thinking to:

  1. adopt proposed option 1: recovery through the residual charge; or
  2. adopt option 2: allocate connection asset decommissioning costs to all customers connected to the asset, regardless of the reason for decommissioning; or
  3. adopt a combination of these two options.

 

Answer: 

Thank you for your question, and for taking the time to provide your feedback on our consultation paper and summary and response. 

We agree that part of the summary is a bit confusing.  What we mean to say is, based on the submissions we received, particularly relating to the “last man standing” problem, our thinking now is to retain the status quo approach of socialising decommissioning costs across all load customers, being currently via the interconnection charge (option 1).  Under the new TPM that would mean decommissioning costs for connection assets would be socialised through the residual charge, unless we have an agreement outside the TPM (for example an investment contract) under which the relevant customer(s) have agreed to pay all or part of the costs.

We will update the response paper soon to clarify this.

 

23 September 2020 (Trustpower) - forthcoming workshops on TPM congestion charge

Question: 

The proposed transmission congestion charge is a new charge. If adopted it will partially replace a charge that has been in place for many decades. Any congestion charge recommended by Transpower as part of the TPM will directly affect our business. For this reason our Board will expect us to participate fully in its design. 

Trustpower is pleased I have been directly invited to participate in one of the two workshops on 6 October as a representative of embedded generators.  However, a number of other members of our transmission pricing team are also keen to have real time access to the discussions in these workshops rather than wait for Transpower to upload the videos which, in any event, may not capture the full tenor of the meeting. 

We note it is easy for the meeting host to mute any observer who attempts to ask questions so there is no risk to the efficient conduct of the meeting by allowing attendance in this manner. 

In our view providing real time access will enhance the quality of our submission to you on this important topic. This is particularly the case given the unconventional process you have proposed and the limited time you have afforded (two weeks) for making what you have termed a ‘cross-submission’. 

Could you please advise if it is possible for Trustpower and its advisers to attend the proposed online workshops on the transmission congestion charge as an observer. 

We believe this will enhance the accessibility of the process.

 

Answer:

Thank you for your letter dated 23 September. We appreciate Trustpower’s interest in Additional Component D: Transitional Congestion Charge and are very grateful you’ve made time to be available to participate in one of our two workshops on 6 October.

Transpower engaged John Hancock to facilitate these sessions including because he has built up considerable experience in running such forums using virtual tools. We are employing the virtual approach in part to de-risk our plans given the uncertainty of how COVID might next impact the country and/or parts of the country. But also this format makes it easier for the experts we have invited to participate to do so around their other commitments.

John’s experience is that he has tried and tested allowing observers, and learned it changes the dynamic of the session - it turns into a set of presentations rather than a full and open discussion.  Further, if we brought in others from Trustpower, we would have to make the same offer to all interested parties. We would then have to address the practicality of muting and managing everyone while still trying to focus on the 9 original invitees. It is a technical workshop with expert invitees so we have to focus on them for it to work. We are very mindful that the input of those experts we have invited will be invaluable in informing our own thinking, process and, if necessary, development going forward.

We will publish the unedited recordings from both sessions to our webpage the morning following the workshops – so on 7 October. The risk that the full tenor of the workshops is not captured is small.  

We appreciate that two weeks is a short period for the ‘cross-submissions’ stage, however our timelines across the full TPM Development scope are tight in all areas and we are mindful of the subsequent process steps to come if our June proposal is to include a TCC proposal.

I’m sorry we cannot, on balance, accommodate your request. We will publish your letter and this response on our ‘TPM questions and answers’ webpage.

7 September 2020 (MEUG) - Breakdown of costs by individual GXP and GIP

Question:

Most interesting would be the breakdown of costs by individual GXP and GIP. If this information is already disclosed please let me know where it can be found. If not disclosed at such a granular level, is there readily accessible data to fill in parts of the table below that would assist?

If the structure of the table doesn’t correctly capture how CIIC’s and Part 4 regulated assets are treated as part of connection assets, please call to discuss or modify the table below.

Note I’m assuming the acronym used is CIIC’s. I think it used to be New Investment Contracts (NIC’s).

Answer:

Connection charge information you have requested is not disclosed publicly.  Having discussed your question with you, we understand that the following information (at an aggregate level, in dollar amounts not percentages) will serve your purpose.

*Other includes assets created under investment contracts (TWA, CIC, NIA, AAGA) as well as customer owned assets (e.g. HTI_TMU) leased (e.g. KUM line) and prudent discount assets.

 

7 September 2020 (MEUG) – Questions addressing the Connection Charges Consultation

Regarding focus area 7: Connection asset decommissioning costs

Q1: Can you outline scenarios and past examples where decommissioning costs have been involved (in addition to Pike River mentioned in the paper).  

A1: Some examples where decommissioning costs have or will soon be incurred are:  generation exit – Otahuhu and New Plymouth; industrial exit – Holcim. Another example where we may incur decommissioning costs is: industrial exit – Pike River. In addition, there have been distributor connection reconfigurations that have made some grid assets redundant. As things stand, the grid decommissioning costs arising from events of this type are recovered through the interconnection charge.

  

Q2: What is the definition of decommissioning costs? Does this include a credit for scrap/recovered assets? If the decommissioning costs are a credit, is it planned to share this on the same basis?

A2: This is defined in proposed clause 19A.2(a) of the benchmark agreement as “[Transpower’s] reasonably anticipated costs (including Transpower internal costs) for decommissioning (including removing) any part of the grid that is redundant as a direct result of the Termination Event”.  This covers decommissioning opex, and it is an open question whether it should also cover the stranding cost of the decommissioned assets (accelerated depreciation).  We would welcome stakeholder views on that point.  The point about the scrap/reuse value of the assets is helpful and we suggest it be submitted formally.

 

Q3: What is the materiality of the components of the connection charge (capital/maintenance/overhead split)?

A3: The relativity changes each year depending on various factors. As a representative indication split for the current pricing year (April 2020 to March 2021) is:


Decommissioning opex costs are highly dependent on the extent of assets being decommissioned. Indicatively, to date the decommissioning opex cost for an entire connection location has been of the order $0.5M to $1.5M.

Q4: How does timing fit in? Where there is growth in demand expected, the assets would not be decommissioned without a lot of thought.

A4: Nothing in the proposal obliges Transpower to decommission an asset. If it is considered there would be value in retaining the asset for some future scenario then we will not decommission it and ongoing maintenance costs will be recovered through the residual charge until there is a connected customer. There may be a case for adding a time restriction to the clause (e.g. decommissioning costs are only recoverable through the agreement if decommissioning commences within X years of the Termination Event). We would welcome stakeholder views on that point.

 

Q5: Under option 2, would a party signing up for supply need to do due diligence on the other parties sharing the connection assets?

A5: That would be up to the connecting party. We think it would be very rare that a shared asset would be decommissioned if only one customer exited. It would probably only occur if some grid optimisation were sensible with the reduced number of connected parties, such that the shared asset is made redundant. We acknowledge there is a “last one to leave” risk.  

 

Q6: It is likely EDBs will look at applying the same approach. Has the appropriateness of this been assessed?  

A6: It is beyond the scope of the TPM development project to assess distributor pricing policies or what changes may be made to them in future. 

 

Regarding focus area 8: First-mover disadvantage

Q7: Paragraph 102 rightly points out these proposals have parallels with the proposed Benefits Charge. Can we have some explanation and discussion around how all this may work?

A7: Paragraph 102 is talking about Type 2 first mover disadvantage as investment contracts are very rarely used for interconnection investments. First mover disadvantage has potential implications for both connection and benefit-based investment assets. How the treatment may best interact is something we will need to turn our mind to as we develop proposals for the benefit-based charge. We would welcome any stakeholder feedback on this matter in the meantime.

 

Q8: The Type 1 proposal (paragraphs 104 to 106) brings back memories of the old Electric Power Board’s minimum annual guarantee provisions which involved proportioning as more consumers connected. Has the dust been blown off these rules as to an appropriate allocation mechanism? Can we be talked through the example or before the meeting sent a table showing how charge components would be calculated and cashflows work over the 10 years for the 2 cases (C1 then C2, and second case C1, then C2 and then C3)?  

A8: The strawman proposal to address Type 1 first mover disadvantage was not informed by any pricing strategy the old Electric Power Board may have employed.  It is a potential way to ensure subsequent customers contribute to the capital cost of the connection assets they connect to rather than getting a “free ride”.  Extending the example in the consultation paper and assuming C1’s NIC payments end after 10 years, C2 enters at year 4 and C3 enters at year 8, the customers’ net payments (NIC + FAC) look like this:

Q9: Type 2 (paragraphs 107 to 12) opens up much broader, but important design issues such as:

Q9.1 The shareholder funds additional investment for the future. Alternatively one would expect a risk-free rate of return.  

A9.1: How investments are funded and the permitted returns on those investments is a Part 4 Commerce Act matter and outside of the scope of TPM development. 
 
Q9.2: It would be useful to have a discussion on the incentives, and how those can be reflected in connection charges, on any discretion Transpower may have to over-build connection assets in anticipation of Transpower’s view further customers will connect in the future.  We think this is an important factor that is not addressed in the consultation paper. 

A9.2: The constraints on, and incentives affecting, Transpower’s grid investment decisions are matters for Transpower’s regulation under Part 4 of the Commerce Act and outside the scope of the TPM.  If an investment is major capex, the investment needs to pass the grid investment test under Transpower’s Capex Input Methodology.  For base capex, Transpower has a fixed allowance for its whole regulatory control period, and regulated incentives to prudently underspend (rather than overspend) relative to the allowance baseline. Many connection investments are carried out under investment contracts, which must be agreed with the funding customers.

 

Regarding additional components C and F

Q10: Additional component C is charges for connection investments to use a method substantially the same as for benefit-based charges. Additional component F is allocation of opex.  The paper says there is no compelling reason to adopt these (paragraph 9).  It’s possible that in the details of the yet to be designed benefit-based charges regime there will be innovative approaches relevant to additional components C and F. Can the timeline be adjusted to allow reconsideration of these after we see the details of the for benefit-based charge regime?  

A10: We agree that there are various potential interrelationships and dependencies between the different parts of the new TPM. This includes tat the approach we develop for the benefit-based charges may impact how we should deal with additional components C and F. This is something we will consider as part of the benefit-based charge development, on which we plan to consult in November-December. We welcome further stakeholder feedback on any potential interactions such as those detailed in this question.

 

18 August 2020 (IEGA NZ) - Transitional peak charge in project timeline

Question: Thanks for your regular and thorough communications on this project. I read with interest the TPM Development project timeline. It is not clear to me how work on the transitional peak charge component of the TPM Guidelines is incorporated into the project timeline. Appreciate hearing from you on this.

Answer: Thanks for your question. We’re glad to hear our communications are welcome. We are yet to make a decision on how we will approach Additional Component D: transitional congestion charge and will update all stakeholders as soon as a decision has been made.