News
27 Feb 2023
Transpower releases half-year results
Transpower New Zealand today released its financial results for the six months ending 31 December 2022.17 Feb 2023
Transpower completes bypass of Redclyffe substation
Transpower has advised that it has completed the bypass of its flooded Redclyffe substation this afternoon.17 Feb 2023
Transpower expects to complete bypass of flooded substation today
Transpower expects to complete bypass of flooded substation today.16 Feb 2023
Transpower continues to work with lines companies to restore power in the Hawke's Bay and Tairāwhiti regions
Transpower has advised that it has continued to increase the amount of power available to local lines companies in the Hawke's Bay and Tairāwhiti in the wake of Cyclone Gabrielle.14 Feb 2023
Limited power restored to Hawkes Bay and Gisborne
Transpower has advised that it has been able to restore some power to parts of Hawkes Bay and Gisborne following the outage this morning resulting from Cyclone Gabrielle.14 Feb 2023
Transpower declares Grid Emergency
Transpower has declared a Grid Emergency following the loss of electricity supply to Hawkes Bay and Gisborne as a result of extreme weather from Cyclone Gabrielle.01 Feb 2023
Second stage of $144m grid project brought forward in response to electricity demand increases
Transpower has announced it will action stage two of its Waikato-Upper North Island Voltage Management Project.30 Jan 2023
Transpower releases Q2 performance report
Transpower today released its second quarter operational and financial performance results for the three months ended 31 December 2022.