Cable joint repair project - Auckland

Last updated: 18 Feb 2025

Image
Brownhill-Pakuranga Joint Bay locations Oct 2024

What are we doing? 

Transpower is replacing joints on an underground electricity cable in Auckland between our Brownhill and Pakūranga substations. This work began in June 2024 and will be carried out over the next two to three years.

Why are we doing it?

Following two faults in cable joints on this circuit in the past three years, we are taking a prudent approach by replacing all joints on the cable. Replacing these joints returns this important cable to its intended condition, so it can operate effectively for its expected 30–40-year life. Ensuring the cables can reliably supply electricity to Auckland and Northland is essential. 

We assessed a range of other remediation options for the cable and concluded that replacing the joints will give the best overall outcome for electricity users in the region.

How will it affect you?

This is a complex project with some challenging excavation sites, which will cause traffic disruptions. 

We are mindful of our work in the community and want to understand your concerns and minimise the impacts of our work where we can.

More information for local residents and businesses is included in these information sheets:

We have several mitigations underway to minimise the impacts of this work, including working six days a week to shorten the overall length of time for the project. We cannot undertake this work at night.

Safety for the public and for our workers is paramount, and our sites will be fenced and monitored. 

You can contact the team by emailing us at [email protected] or calling 0800 222 553 or 021 241 8740 to talk to our Community Engagement Lead on this project. 

We will communicate directly with local communities, mana whenua and other stakeholders as the project progresses and we will also provide regular updates on this page.

Secure electricity supply

The work we are undertaking will not cause power outages. Electricity supply into Auckland and Northland is secure and will continue to be secure during the works. This is because there is a companion cable on the circuit between Brownhill and Pakūranga, and we have recently built a temporary bypass line in north Waikato to provide additional security and ensure peak demand can be met. 

Timeline and updates

We are working at different sites along the cable route and completion dates are indicative.

LocationJoint Bay IDCompletion (indicative)
Year one - June 2024 to June 2025
Sandstone Road, Whitford 5, 6Completed
Caldwells Road, East Tamaki Heights9, 10June 2025
Kilkenny Drive13March 2025
Te Irirangi Road15May 2025
Tiger Drive16June 2025
Year two - June 2025 to June 2026
Brown Hill Road1, 2, 3Mar 2026
Whitford Park Road5Mid 2026
Caldwells Road8Mid 2026
Point View Drive11Mid 2026
Dunvegan Rise12Mid 2026
Armoy Drive14Mar 2026