Resources
Displaying 1 - 6 of 6
Last updated: 03 Jul 2023
SO full report - Hawkes Bay loss of supply.pdf
… 13 Table 3 - Estimated VoLL (08:00 14/02/23 - 16:30 10/03/23) … time to restore service, the estimated value of lost load (VoLL4) for the duration of the grid emergency (08:00 14/02/23 - 16:30 10/03/23) is significant. VoLL was determined by comparing the load successfully …
SO full report - Hawkes Bay loss of supply.pdf
(PDF 2.07 MB)
Last updated: 22 May 2023
System operator initial report Hawkes Bay loss of supply.pdf
… to restore service means the estimated value of lost load (VoLL) will be significant. A calculation of VOLL will be included in the final report. TRANSPOWER NEW … network TUI Tuai substation Unison Unison Networks VoLL Value of lost load WHI Whirinaki substation WRA Wairoa …
Last updated: 25 Mar 2025
Orion - SOSFIP Review - Issues Paper Questions - March 2025
… at more than $37.5 million using the Value of Lost Load (VoLL) set out in the Code, with other estimates suggesting …
Orion - SOSFIP Review - Issues Paper Questions - March 2025.pdf
(PDF 274.67 KB)
Last updated: 05 Jul 2024
System operator preliminary report - Northland loss of supply v1.pdf
… network means the estimated value of lost load (VoLL) will be large. A calculation of VoLL will be included in the final report. 4.4 Restoration … Upper North Island Reactive Power Controller VLD Vector VoLL Value of lost load TRANSPOWER NEW ZEALAND | System …
Last updated: 25 Mar 2025
Meridian SOSFIP Review - Issues Paper Questions - March 2025
… GWh 1,404 1,083 -321 -23% Dem Resp GWh 240 108 -132 -55% VoLL GWh - - 0 - CO2 Emissions kT 4,500 2,593 2,369 -224 -9% …
Last updated: 06 Sep 2024
Northland Loss of Supply Investigation (System Operator-Commissioned).pdf
… Upper North Island Reactive Power Controller VLD Vector VoLL Value of lost load 22 Appendix B: Assets out of service …