RCP3 updates and disclosures

Integrated Transmission Plan (ITP)

The ITP is a suite of documents outlining our 10-year plans. It brings together our services, expenditure forecasts and asset management plans. See downloads below. 

Annual disclosures 

2023

TitleDescription
Service Measures Report 2023Defines our service offering and performance targets, and explains how we use these in our business
Asset Management Plan 2023Explains our asset management framework, our management of each asset class, and includes a summary of planned works
Transmission Planning Report 2023Identifies backbone grid and regional development plans 
RT01 Expenditure forecastsSets out our forecast capital and operating expenditure to the end of RCP4
ITP 2023 compliance reportExplains how the ITP meets our regulatory requirements

2022

TitleDescription
RCP4 Consultation document Concise, accessible overview of our plans - in 2022, our RCP4 consultation document meets the requirements of the ITP Narrative
Service Measures Report Defines our service offering and performance targets, and explains how we use these in our business
Asset Management Plan Explains our asset management framework, our management of each asset class, and includes a summary of planned works
Transmission Planning Report Identifies backbone grid and regional development plans 
ITP Schedules Sets out our forecast capital and operating expenditure to the end of RCP4
ITP Compliance Report Explains how the ITP meets our regulatory requirements
ITP GlossaryAccompanies the reports contained within the ITP

2021

Title Description
ITP NarrativeConcise, accessible overview of our plans
Grid Outputs ReportDefines our service offering and performance targets, and explains how we use these in our business
Asset Management PlanExplains our asset management framework, our management of each asset class, and includes a summary of planned works
Transmission Planning ReportIdentifies backbone grid and regional development plans 
ITP SchedulesSets out our forecast capital and operating expenditure to the end of RCP4
ITP Compliance ReportExplains how the ITP meets our regulatory requirements
ITP GlossaryAccompanies the reports contained within the ITP
 

2020

Title Description
ITP NarrativeConcise, accessible overview of our plans
Grid Outputs Report Defines our service offering and performance targets, and explains how we use these in our business (formerly called the Services Report)
Asset Management PlanExplains our asset management framework, our management of each asset class and includes a summary of planned works
Transmission Planning ReportIdentifies backbone grid and regional development plans (formerly called the Annual Planning Report)
ITP SchedulesSets out our forecast capital and operating expenditure to the end of RCP4
ITP Compliance ReportExplains how the ITP meets our regulatory requirements
ITP GlossaryAccompanies the reports contained within the ITP

Annual disclosures under Individual Price-Quality Path (IPP) and Information Disclosure (ID) regulation

Year

IPP Disclosures

(including SMAR update)

Information DisclosurePricing Compliance
2020/21

RCP3 - ACS disclosures 2020-21

RCP3 - Information to accompany ACS 2020-21

ID 2020-21Directors Certificate
2021/22

RCP3 - ACS disclosures 2021-22

RCP3 - information to accompany ACS 2021-22

Kinleith feeder tripping amendment to disclosure years 19-20 and 20-21

RCP3 Information requirements workbook for proposed SMAR update (MCP)

ID 2021-22Directors Certificate
2022/23

RCP3 - Information requirements workbook for proposed SMAR update (E&D)

RCP3 - ACS disclosures 2022-23

RCP3 - information to accompany ACS 2022 - 23

RCP3 - ACS information to accompany ACS DY 2022 for AP3 revision

ID 2022-23Directors Certificate
2023/24

RCP3 - ACS disclosures 2023 - 24

RCP3 - information to accompany ACS 2023 - 24

ID 2023 - 24

ID 2023-24 Tab G5 Update

Directors' Certificate
2024/25   

Other documents

The Commerce Commission issued three information gathering notices under s53ZD of the Commerce Act 1986 along with its Individual Price-Quality Path (IPP) determination for RCP3. Documents provided to the Commission in response to these notices will be posted in this section, along with event reports for material unplanned interruptions (under the IPP) during the regulatory period. 

Cost estimation

Customer Engagement

Asset Health and Network Risk

Post per-event unplanned interruption report (IPP determination 2020 - 2025, clause 26)