TPM development updates (August 2020 - April 2022)

27 April 2022: Indicative pricing update

08 Nov 2021: Amended diagram in TPM proposal

08 Oct 2021: Electricity Authority announce consultation on proposed new TPM

20 Sep 2021: Benefit Based Charge resubmission to the Electricity Authority published

30 Aug 2021: Non-BBC TPM resubmission to the Electricity Authority published

09 Aug 2021: TPM proposal to Electricity Authority published

01 July 2021: TPM proposal delivered to Electricity Authority

02 June 2021: Our plan for publishing our final TPM proposal

25 May 2021: TPM checkpoint 2B & 2C process requirement documents published

12 May 2021: TPM battery and storage consultation summary and response published

22 April 2021: TPM battery and storage consultation late cross-submission published

20 April 2021: TPM battery and storage consultation cross-submissions published

13 April 2021: TPM battery and storage consultation submissions published

07 April 2021: TPM indicative pricing and battery and storage consultation

30 March 2021: TPM development battery and storage consultation reminder

22 March 2021: TPM development battery and storage consultation document published

19 March 2021: TPM battery and storage consultation to being 22 March 2021

05 March 2021: TPM Options Consultation summary and response published

23 February 2021: New process requirement documents and Q&A published

17 February 2021: TPM battery and storage consultation

12 February 2021: TCC process requirement documents published

27 January 2021: Electricity Authority Process Requirements

19 January 2021: TPM Options Consultation cross-submissions published

13 January 2021: Cross-submissions for the TPM Options Consultation due 18 Jan

21 December 2020: FMD and PDP summary and response documents published

15 December 2020: TPM Options Consultation submissions published

11 December 2020: New Q&A re TPM Options Consultation deadline & project timeline

08 December 2020: TPM Options Consultation deadline 14 Dec 5pm

02 December 2020: Third online drop-in session transcript & video published

01 December 2020: Third online drop-in session today at 2pm

27 November 2020: Cross-subs published, new transcript & links for drop-in sessions

23 November 2020: Cross-subs closing soon, online drop-in session on Wed, and TCC Summary and Response published

19 November 2020: Submissions published (First Mover Disadvantage and Prudent Discount Policy Consultations)

16 November 2020: Online drop-in sessions begin this week; Consultations closing Wednesday 5pm

09 November 2020: Today we published the TPM Options Consultation (Benefit-Based Charge and Adjustments to Charges)

03 November 2020: Ongoing consultations, updated project timeline, new Q&A

28 October 2020: Two consultations open today

20 October 2020: Connection Charges Consultation published, TCC feedback closes tomorrow, key dates This update was sent on 20 October, but is incorrectly dated 19 October in the newsletter itself. Our apologies for any confusion this may have caused.

13 October 2020: TCC process, and our next consultation

07 October 2020: TCC workshops yesterday, recordings available

29 September 2020: Design Principles published; TCC workshop pre-reading

21 September 2020: Connection charge cross-submission closing; more info on TCC workshops

15 September 2020: Consultation submissions now published

14 September 2020: Consultation closing today; Transitional Congestion Charge workshops announced

07 September 2020: Design Principles feedback published

31 August 2020: Consultation continues

24 August 2020: Connection Charges Consultation

17 August 2020: Timeline, design principles & consultation 

10 August 2020: Work now underway